Date of Publish: 2017-09-19

Data reveal slow progress of PMGSY in north-eastern states

 

Only 192 rural habitations have so far been connected in the current financial year (2017-18) against the target of connecting 1035 unconnected habitations in eight states of Northeast India- Assam, Arunachal Pradesh, Meghalaya, Manipur, Mizoram, Nagaland, Tripura and Sikkim- under the Prime Minister Gram Sadak Yojana (PMGSY), India’s flagship programme of rural road connectivity for the year.

Only two habitations have been in Arunachal Pradesh against the target of 50 habitations for the current year even though 591.575 km of road against the targeted length of 1200 km have been completed. Not a single habitation has been connected so far in Mizoram, Nagaland and Sikkim in the current financial year while 42.5 km ( target 50 km) in Nagaland, 28.525 km ( Target 500 km) in Mizoram and 113.185 ( target 400 km) have been constructed.

Official data show that against the targeted construction of 6250 km length of rural road during current fiscal only 1035 km length of roads have been constructed in these eight states so far under this flagship programme.

In 2016-17, altogether 385 habitations were connected against the target of 710 habitations. However, data displayed on the website of the National Rural Roads Development Agency show that number of connected habitations surpassed the number of targeted habitations in 2015-16 and 2014-15. In 2015-16, altogether 589 habitations were connected against the target of 485 habitations and in 2014-15, a whooping 829 habitations were connected against the target of 328 habitations.

PMGSY IN NORTH EAST DURING 2017-18 (TILL SEPTEMBER 18)

PMGSY IN NORTH EAST DURING 2017-18 (TILL SEPTEMBER 18)
STATE TARGETTED LENGTH COMPLETED LENGTH TARGETTED HABITATIONS CONNECTED HABITATIONS
Arunachal Pradesh 1200 591.575 50 2
Assam 2000 188.583 650 106
Manipur 1000 168.48 85 53
Meghalaya 450 52.912 60 14
Mizoram 500 28.525 55 0
Nagaland 50 42.5 0 0
Sikkim 400 113.185 35 0
Tripura 650 162.662 100 17
India 57,000 13,721.72 16,660 3,676

 

PMGSY IN NORTH EAST DURING 2016-17

PMGSY IN NORTH EAST DURING 2016-17
STATE TARGETTED LENGTH COMPLETED LENGTH TARGETTED HABITATIONS CONNECTED HABITATIONS
Arunachal Pradesh 650 1360.509 40 1
Assam 750 929.515 500 315
Manipur 790 1485.846 40 26
Meghalaya 400 368.865 45 22
Mizoram 200 298.08 5 0
Nagaland 150 395 0 0
Sikkim 150 247.422 20 3
Tripura 400 405.622 60 18
India 48,812 47,446.84 15,000 11,606

PMGSY IN NORTH EAST DURING 2015-16

PMGSY IN NORTH EAST DURING 2015-16
STATE TARGETTED LENGTH COMPLETED LENGTH TARGETTED HABITATIONS CONNECTED HABITATIONS
Arunachal Pradesh 511 306.14 26 14
Assam 810 989.48 338 403
Manipur 390 364.553 26 29
Meghalaya 130 150.96 20 24
Mizoram 104 117.32 6 4
Nagaland 175 93.5 6 0
Sikkim 156 390.769 13 57
Tripura 250 357.326 10 58
India 33,649 35,155.01 10,117 9876

 

PMGSY IN NORTH EAST DURING 2014-15

PMGSY IN NORTH EAST DURING 2014-15
STATE TARGETTED LENGTH COMPLETED LENGTH TARGETTED HABITATIONS CONNECTED HABITATIONS
Arunachal Pradesh 450 7 14 0
Assam 720 1276.942 228 661
Manipur 236 301.68 10 35
Meghalaya 105 30.724 15 7
Mizoram 115 37.14 5 0
Nagaland 160 198.3 1 0
Sikkim 100 165.247 5 47
Tripura 250 239.213 50 79
India 21,775 38,055.43 4,688 10,998

The primary objective of the PMGSY is to provide Connectivity, by way of an All-weather Road to the unconnected habitations in the rural areas with a population of 500 persons and above in Plain areas and unconnected habitations with a population of 250 persons and above in the hill states.

The PMGSY Guideline states that “In the case of Hill States, the estimates for new construction works may be prepared in two parts wherever circumstances so require. As such:

(a) The first stage will consist of formation cutting, slope stabilization, protection works and drainage works. If black topping at the second stage is intended, it may be taken up after two rainy seasons have elapsed to ensure adequate stabilization of the side slopes. The second stage will include the WBM layers and bituminous surface course. The habitations concerned will not be counted as ‘connected’ till the second stage is taken up.

(b) Where State Government agrees as a policy that ‘unsealed’ surfaces are adequate in certain conditions like low traffic, the formation cutting, slope stabilization and protection works, complete drainage works and appropriate surface course treatment (to ensure all -weather connectivity) will all be included in the first stage and work executed. In such cases, the habitations will be counted as ‘connected’ on completion of the first stage itself, as there will be no second stage.

Comment


REVIEW OF SANGAM: THE JHANSI LEGACY Manipur and Trinidad: An unlikely novel connection
Myanmar Opium Survey 2020: Despite 11 per cent drop in cultivation, country's drug economy continues to fuel armed conflict
Some selected sculpted images of Chamunda found in Assam : A glimpse into their iconographic features
Assam HDR 2014: Limited scope for work participation and high unemployment rates pushing youth and women to migrate outside the state
Harbingers of tranquillity – a photo story by Girimallika Saikia
Political lines of Raijor Dal and AJP have lessened BJP’s worries of a grand alliance of anti-CAA parties in Assam
Traditional Knowledge System enhances children’s learning